Code is usually what migration plans worry about; content is what decides the go-live weekend. Adobe's Content Transfer Tool (CTT) moves content from an AEM 6.3 or later instance, on-premise or AMS, to AEM as a Cloud Service, managed through Cloud Acceleration Manager.

How a transfer works

  1. Create a migration set in Cloud Acceleration Manager: the paths to move. A project can hold up to ten migration sets; a set expires after about 45 days without activity.
  2. Extraction copies the content from the source instance into a temporary cloud storage area Adobe provides.
  3. Ingestion loads the migration set into the target Cloud Service environment.
  4. Top-ups repeat both steps for changes only: extract with overwrite disabled, ingest with wipe disabled, so the delta lands on top of what is already there.

Check the limits before you plan dates

LimitWhat Adobe documents
Source versionAEM 6.3 or later.
Segment storeLess than 750 million JCR nodes and up to 500 GB on author; 50 GB on publish. Larger needs a support ticket with Adobe.
Total repository (segment + data store)Designed for up to 20 TB with a file data store; S3 and Azure data stores can go beyond with the optional pre-copy step, which also speeds up large transfers.
Lucene indexes25 GB in total, excluding /oak:index/lucene and /oak:index/damAssetLucene.
Immutable pathsCTT cannot migrate content in immutable paths such as /apps; code travels through Cloud Manager.
MongoDBProperty values cannot exceed 16 MB; run Adobe's oak-run check before extraction.

If you are near any limit, open the support ticket early: it is lead time you cannot compress later.

Planning the freeze

  • Run the first full extraction and ingestion weeks before go-live, to stage or a dev environment, and time both steps.
  • Agree with the business how long authors can stop publishing. Adobe recommends frequent differential top-ups to shorten that freeze.
  • Schedule top-ups so the last one before cutover is small: daily in the final week is common.
  • Fix asset validation findings from Best Practices Analyzer (missing original renditions or nodes) before the first extraction, or they travel with the content.
  • Plan users and groups separately and confirm with your team how they map to Adobe IMS sign-in on Cloud Service.

On the go-live weekend

  1. Freeze authoring on the source.
  2. Run the final top-up extraction and ingestion.
  3. Smoke-test author and publish on Cloud Service, including recently changed pages and assets.
  4. Switch DNS and keep the source read-only for an agreed period.